CONSTRUCTION UPDATE: JANUARY 5, 2018

We are making great progress, despite what the weather man is telling us! Can you believe that there are an average of 35-40 contractors on sight daily? Below are some current pictures of what is happening.

A new wall was constructed in our surgery waiting area in preparation for the tie-in for the northeast addition (where the new Emergency Department will be).  See outside view for tie-in:

On the southwest addition, here is a picture from inside the courtyard area showing patient room windows.

First floor of the southwest addition shows fireproofing being done to the steel beams.

A quick look into the new dining area and where the food service equipment will be placed

Southwest addition public elevator and opening for commons’ stairwell.

Outside shot facing Clark street.  Brick will start to be installed starting Monday, January 8th!